Welcome to The ME2045 Group J Crane Project Blog page!


This entire site is to give a guide to Group J`s efforts to design a small portable crane for use in disaster relief before our final submission of work and our presentation.

Following our first meeting (See the Minute Meetings Topic for reference) the following positions have been allocated;

D.Scriven Project Manager
R.Sidhu Chief Designer
H.Singh Sall Finnance Officer
J.Sidhu Materials Specialist
R.Shukla Stress Analysis

For Our Progress up to date please see the Project Plan below and then head to the relevant topic and we hope you find our work interesting!

Wednesday, 28 April 2010

Calculations For Buckling

Shown below are the calculations carried out to find out if the crane stucture would buckle and fail. The calculations were carried out on the members which would be likely to buckle under a compressive load.





The calculations prove that the members under compressive load would not buckle at 1.5 times the recommended lifting capacity.